Riot’s $28 billion AI lease gives Anthropic a veto on voluntary power cuts

Quick Take

  1. Riot's binding Corsicana lease requires Anthropic's consent for voluntary cuts to its tenant load; mandatory grid orders remain exempt.
  2. The planned 910 MW is targeted for phased delivery through July 2028, with rent beginning pad by pad.
  3. The $28 billion contract value spans future revenue; construction costs, financing and possible rent credits shape retained cash.

Riot Platforms' Corsicana lease with AI company Anthropic became binding Nov. 4, making voluntary curtailment of the tenant's power load subject to its consent. The agreement puts a tenant-approval requirement around an operating choice the Bitcoin miner has used in its power strategy.

Under the terms disclosed in Riot's quarterly filing, Riot needs Anthropic's consent to curtail the tenant's load or enroll the premises in voluntary demand-response programs. Mandatory orders from the utility or grid operator are exempt.

Who decides when Corsicana powers down?

Riot commits planned capacity to AI rent. The lease sets different rules for voluntary cuts and mandatory orders.

Choose the reason for reducing load

Applies to Riot's choice to curtail the tenant's load or enroll the premises in voluntary demand response.

The approval gate covers the leased tenant load, rather than a companywide ban on mining curtailment.

Capacity remains planned. The issuer summarizes the lease. Rent may be deferred up to 60 days per pad if tenant modules are absent. No quantified credit loss is implied.

Sources and evidence

Sources

  1. Riot Q3 2026 Form 10-Q, Notes 1 and 3; Item 5
  2. Riot Q3 2026 presentation, slides 8-9

Supporting facts

  • Riot Corsicana signed the lease with Anthropic PBC on October 28, 2026; it became effective and binding on November 4 after board approval and approval of technical specifications by third-party consultants. [1]
  • The Corsicana premises are expected to provide 910 MW of critical IT capacity, delivered in three phases rather than operating at full leased capacity today. [1] [2]
  • Without Anthropic's consent, Riot Corsicana may not curtail the tenant's power load, except as mandatorily ordered by the utility or grid operator, or enroll the premises in voluntary demand-response programs. [1]
  • Phase 1 targets 400 MW, with the first block commencing June 28, 2027 and the full phase September 11, 2027; Phase 2 targets 200 MW fully commencing January 28, 2028; Phase 3 targets 310 MW on July 30, 2028. [1]
  • Riot's presentation says rent begins when each powered pad is delivered, with a possible extension of up to 60 days if the tenant's modules are not yet installed, and describes rent on delivered capacity as take-or-pay regardless of utilization. [2]
  • Riot must construct and deliver the power and site infrastructure at its own cost and maintain the power infrastructure; Anthropic bears electricity, taxes, insurance and site expenses under the triple-net lease. [1]

Method

Qualitative contract and responsibility diagram using the issuer's disclosed terms. Arrows show power delivery, rent obligations and consent/order pathways, not measured electricity or cash flows. Capacity remains planned and delivery phased.

Scope

Capacity remains planned. The issuer summarizes the lease. Rent may be deferred up to 60 days per pad if tenant modules are absent. No quantified credit loss is implied.

Infographic by CryptoSlate

The agreement, signed Oct. 28, covers a planned 910 megawatts of critical IT capacity. Riot's earnings presentation puts initial-term contract revenue at approximately $28 billion, including annual escalators before amortization of tenant reimbursements. That figure spans future lease revenue, rather than cash already received or current profit.

The operating restriction changes the choices behind that revenue. Riot's mining strategy includes selling unused or uneconomic contracted power at Rockdale and voluntarily reducing consumption at Rockdale and Corsicana during Texas summer peaks. The company reported $25 million in companywide power-curtailment credits in the third quarter; peak-demand transmission savings separately lower subsequent-year bills.

The lease illustrates the shift from mining's flexible power use toward AI load subject to tenant consent. Anthropic bears the leased site's electricity bill, and the disclosures do not quantify any curtailment income Riot might forgo.

Rent follows delivery

The expected 910 MW must still be delivered. Riot targets the first block for June 28, 2027, with the full 400 MW first phase due that September. Another 200 MW is targeted for January 2028 and the final 310 MW for July 2028.

Base rent starts at $130 per kilowatt of delivered critical IT capacity per month, increasing 3% annually. The initial term begins with the first block and ends in the month containing the fifteenth anniversary of Phase 3's commencement.

Rent begins pad by pad, with up to a 60-day extension if Anthropic's modules are not installed at delivery. Once capacity is delivered and rent commences, the presentation describes payment as independent of utilization. Riot must build the site and power infrastructure and maintain the power infrastructure; Anthropic bears electricity, taxes, insurance and site expenses.

The gap between construction and rent also featured in CryptoSlate's earlier coverage of Riot's separate Rockdale financing. At Corsicana, Riot estimates roughly $5.5 billion of hard costs, including site work and tenant module reimbursements.

Riot must reimburse Anthropic for eligible module costs, up to $4 million per megawatt of critical IT power actually achieved, subject to financing on market terms reasonably acceptable to Riot. If financing remains unavailable after commercially reasonable efforts, Riot instead credits Anthropic's rent. Those credits amortize the reimbursement plus 12% annual interest over the remaining initial term, reducing rent collected in cash.

Capacity more than 60 days late triggers escalating rent credits, capped at 270 days of base rent for undelivered blocks in the relevant phase. A phase delayed beyond 270 days can be terminated on 30 days' notice, subject to cure rights and extensions for force majeure or tenant-caused delays.

Editorial credits

Liam 'Akiba' Wright
Liam 'Akiba' Wright
Editor-in-Chief CryptoSlate

Also known as "Akiba," Liam Wright is a reporter, podcast producer, and Editor-in-Chief at CryptoSlate. He believes that decentralized technology has the potential to make…

Originally published by CryptoSlate on

Read the original on CryptoSlate ↗

Text and images are the property of CryptoSlate and are reproduced here with attribution and a link to the original publication.

More stories

All the latest news